Question and Answers Forum

All Questions      Topic List

Algebra Questions

Previous in All Question      Next in All Question      

Previous in Algebra      Next in Algebra      

Question Number 127607 by bramlexs22 last updated on 31/Dec/20

Answered by liberty last updated on 31/Dec/20

 A ⇒24 days    B ⇒ 15 days   C⇒ 12 days   A and B started worked 3 days ⇒ 3×((1/(15))+(1/(12))) work   ⇒(1/5)+(1/4) = (9/(20)) works    remaining works = 1−(9/(20)) = ((11)/(20))   A complete the remaining works⇒n ×(1/(24))=((11)/(20))   ⇒ n = ((24^6 ×11)/(20^5 )) = ((66)/5) days = 13(1/5) days

A24daysB15daysC12daysAandBstartedworked3days3×(115+112)work15+14=920worksremainingworks=1920=1120Acompletetheremainingworksn×124=1120n=246×11205=665days=1315days

Terms of Service

Privacy Policy

Contact: info@tinkutara.com