Question and Answers Forum

All Question   Topic List

Question Number 136063 by liberty last updated on 18/Mar/21

$$ \\ $$ A and B can do a job in 10 days and 5 days, respectively. They worked together for two days, after which B was replaced by C and the work was finished in the next three days. How long will C alone take to finish 40% of the job?\\n

Answered by nadovic last updated on 18/Mar/21

A′s Rate of work = (1/(10))  B′s Rate of work = (1/5)  Combined Rate of work = (1/(10)) + (1/5)                                                     = (3/(10))  ∴ A and B would complete the work       together in ((10)/3) days.  But B was replaced after 2 days.  Now,  (2/((10/3))) ×100= 60%    So A and B finished 60% of the job   and A and C will work on the 40% left  which they finished together in 3 days.  ⇒  it will take A 4 days to finish 40%          of the job, working alone.    Suppose C can finish the remaining  40% alone in x days, then                   ((0.4)/x)  +  ((0.4)/4)  =  ((0.4)/3)                   x  =  12 days   Hence, C can finish 40% of the work   alone in 12 days.

$${A}'{s}\:\mathrm{Rate}\:\mathrm{of}\:\mathrm{work}\:=\:\frac{\mathrm{1}}{\mathrm{10}} \\ $$ $${B}'{s}\:\mathrm{Rate}\:\mathrm{of}\:\mathrm{work}\:=\:\frac{\mathrm{1}}{\mathrm{5}} \\ $$ $$\mathrm{Combined}\:\mathrm{Rate}\:\mathrm{of}\:\mathrm{work}\:=\:\frac{\mathrm{1}}{\mathrm{10}}\:+\:\frac{\mathrm{1}}{\mathrm{5}} \\ $$ $$\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:=\:\frac{\mathrm{3}}{\mathrm{10}} \\ $$ $$\therefore\:{A}\:\mathrm{and}\:{B}\:\mathrm{would}\:\mathrm{complete}\:\mathrm{the}\:\mathrm{work}\: \\ $$ $$\:\:\:\:\mathrm{together}\:\mathrm{in}\:\frac{\mathrm{10}}{\mathrm{3}}\:\mathrm{days}. \\ $$ $$\mathrm{But}\:{B}\:\mathrm{was}\:\mathrm{replaced}\:\mathrm{after}\:\mathrm{2}\:\mathrm{days}. \\ $$ $$\mathrm{Now},\:\:\frac{\mathrm{2}}{\left(\mathrm{10}/\mathrm{3}\right)}\:×\mathrm{100}=\:\mathrm{60\%} \\ $$ $$ \\ $$ $$\mathrm{So}\:{A}\:\mathrm{and}\:{B}\:\mathrm{finished}\:\mathrm{60\%}\:\mathrm{of}\:\mathrm{the}\:\mathrm{job}\: \\ $$ $$\mathrm{and}\:{A}\:\mathrm{and}\:{C}\:\mathrm{will}\:\mathrm{work}\:\mathrm{on}\:\mathrm{the}\:\mathrm{40\%}\:\mathrm{left} \\ $$ $$\mathrm{which}\:\mathrm{they}\:\mathrm{finished}\:\mathrm{together}\:\mathrm{in}\:\mathrm{3}\:\mathrm{days}. \\ $$ $$\Rightarrow\:\:\mathrm{it}\:\mathrm{will}\:\mathrm{take}\:{A}\:\mathrm{4}\:\mathrm{days}\:\mathrm{to}\:\mathrm{finish}\:\mathrm{40\%}\: \\ $$ $$\:\:\:\:\:\:\:\mathrm{of}\:\mathrm{the}\:\mathrm{job},\:\mathrm{working}\:\mathrm{alone}. \\ $$ $$ \\ $$ $${Suppose}\:{C}\:{can}\:{finish}\:{the}\:{remaining} \\ $$ $$\mathrm{40\%}\:{alone}\:{in}\:{x}\:{days},\:{then} \\ $$ $$\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\frac{\mathrm{0}.\mathrm{4}}{{x}}\:\:+\:\:\frac{\mathrm{0}.\mathrm{4}}{\mathrm{4}}\:\:=\:\:\frac{\mathrm{0}.\mathrm{4}}{\mathrm{3}} \\ $$ $$\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:\:{x}\:\:=\:\:\mathrm{12}\:\mathrm{days} \\ $$ $$\:\mathrm{Hence},\:{C}\:\mathrm{can}\:\mathrm{finish}\:\mathrm{40\%}\:\mathrm{of}\:\mathrm{the}\:\mathrm{work} \\ $$ $$\:\mathrm{alone}\:\mathrm{in}\:\mathrm{12}\:\mathrm{days}. \\ $$ $$\:\:\:\: \\ $$

Commented bybramlexs22 last updated on 18/Mar/21

waw..=thanks

$${waw}..={thanks} \\ $$

Answered by mr W last updated on 18/Mar/21

say A needs a days for the whole job,  B needs b days, C needs c days.  given: a=10, b=5  in two days A and B did  2×((1/(10))+(1/5))=(3/5)  in three days A and C did the rest:  3×((1/(10))+(1/c))=1−(3/5)  ⇒c=30  C needs 30 days to do the whole job.  to do 40% of the job, C needs   0.4×30=12 days

$${say}\:{A}\:{needs}\:{a}\:{days}\:{for}\:{the}\:{whole}\:{job}, \\ $$ $${B}\:{needs}\:{b}\:{days},\:{C}\:{needs}\:{c}\:{days}. \\ $$ $${given}:\:{a}=\mathrm{10},\:{b}=\mathrm{5} \\ $$ $${in}\:{two}\:{days}\:{A}\:{and}\:{B}\:{did} \\ $$ $$\mathrm{2}×\left(\frac{\mathrm{1}}{\mathrm{10}}+\frac{\mathrm{1}}{\mathrm{5}}\right)=\frac{\mathrm{3}}{\mathrm{5}} \\ $$ $${in}\:{three}\:{days}\:{A}\:{and}\:{C}\:{did}\:{the}\:{rest}: \\ $$ $$\mathrm{3}×\left(\frac{\mathrm{1}}{\mathrm{10}}+\frac{\mathrm{1}}{{c}}\right)=\mathrm{1}−\frac{\mathrm{3}}{\mathrm{5}} \\ $$ $$\Rightarrow{c}=\mathrm{30} \\ $$ $${C}\:{needs}\:\mathrm{30}\:{days}\:{to}\:{do}\:{the}\:{whole}\:{job}. \\ $$ $${to}\:{do}\:\mathrm{40\%}\:{of}\:{the}\:{job},\:{C}\:{needs}\: \\ $$ $$\mathrm{0}.\mathrm{4}×\mathrm{30}=\mathrm{12}\:{days} \\ $$

Commented byotchereabdullai@gmail.com last updated on 18/Mar/21

i like it!

$$\mathrm{i}\:\mathrm{like}\:\mathrm{it}! \\ $$

Commented bybramlexs22 last updated on 18/Mar/21

very simple

$${very}\:{simple} \\ $$

Terms of Service

Privacy Policy

Contact: info@tinkutara.com