Question Number 40300 by mondodotto@gmail.com last updated on 18/Jul/18

10 men had the work of cultivating  a farm for 18 days. when (1/3)  of work was done 6 men were reduced.  for how long was the work of cultivating the farm done?

10menhadtheworkofcultivatingafarmfor18days.when13ofworkwasdone6menwerereduced.forhowlongwastheworkofcultivatingthefarmdone?

Answered by MJS last updated on 18/Jul/18

the work =w  w=10m×18d=180md  (1/3)w=60md ⇒ 10 men worked 6 days  180md−60md=120md is left  4m×xd=120md ⇒ x=30 ⇒ 4 men worked 30 days  the work was done within 36 days

thework=ww=10m×18d=180md13w=60md10menworked6days180md60md=120mdisleft4m×xd=120mdx=304menworked30daystheworkwasdonewithin36days

Commented by mondodotto@gmail.com last updated on 18/Jul/18

thank you very much

thankyouverymuch